It is our mission to provide consistent high-performance service to every
Valued Customer. We do this by following our 3-Phase Management
Process, which consists of:
Phase I (Start-up Phase):
Project Set-up
Pull required permits, request payment/performance bond, assign the best suited
Project Manager & Superintendent for the project type.
Develop a site Specific Safety Plan
Establish a safety plan that is specific to the project type, construction method,
materials and project location
Assign an on-site Safety Manager
All LOTT ENERGY projects have a safety manager that is OSHA
30-Hour Certified
Establish our Material Logistics Plan
In order to ensure that all long lead equipment and material items
are delivered on time, we develop a delivery matrix that is tracked
and update on a daily basis. Our material logistics plan also
includes the use of packaged material kits that contain the exact
quantity of part items for various activities being performed in
specific areas. These material kits are delivered to the project site
when they are needed.
Generate the Required Submittals/Shop Drawings
As soon as a project is awarded our Engineering Team begins
the submittal/shop drawing process. All submittals/shop drawings
are indexed and bound by specification section. We also include
an electronic submission that is bookmarked in pdf format.
Design the Temporary Service, Temporary Power &
Lighting System
The temporary service, power and lighting system is critical to the
construction process. We ensure that the temporary power system
is construction friendly and is installed in a manner so that it doesn't
impact other trades work or cause damage when it is removed. We
know that the temporary system must support construction office
trailers, storage trailers, buckhoists, tower cranes, power for
elevators/escalators, swing stages, etc. We also know that the
other trades need to perform their work and they always need more
power than originally anticipated. Don't worry we take this into
consideration and generally have no issue accommodating their
needs. We also make sure that our temporary power and lighting
system exceeds OSHA standards.
Dissect the Project
Our Engineering Team collects the electronic media from the
Architect/Engineer so they can begin our Installation and
Pre-Fabrication Drawings. Whether required by the GC/CM
or not, at LOTT ENERGY every project goes through Building
Information Modeling (BIM) or CAD. This is a critical and
necessary function for us to perform to the level that we expect
of ourselves and most importantly commit to our Customers.
BIM/CAD allows us to identify potential conflicts/clashes with
the structural, architectural or other trade elements. The BIM/
CAD process, even without the participation of all the trades,
is still an effective method for us to plan, layout and coordinate
our work items efficiently and accurately. We believe that we
are better off having over-planned our work in advance, even
if some mistakes are made, than if we didn't plan at all. Our
Installation Drawings are fully dimensionalized so that our field
team isn't required to scale drawings on the jobsite. We also
coordinate and overlay all of the structural, architectural, civil,
mechanical, plumbing, fire protection, millwork shop drawings,
cabinetry shop drawings, etc elements. This information is all
transferred to our installation drawing floor plan that includes
all of the necessary information (including our parts/pre-fabrication
assembly list) for our field team to perform an accurate and
efficient installation without flipping drawings or fear that they
are missing information such as rfi's, asi's, addendums, etc.
Staffing Plan
We want to help our Customer push the project. We review
the construction schedule and develop a manload chart that
will allow us to forecast our manpower needs in advance so that
we are never under staffed and can always help drive the project
through the finish line.
Phase II (Construction Phase):
read more Phase II
Phase III (Close-out Phase):
read more Phase III